IMPLEMENTATION trip-
Escuala Taller Santa Maria Josefa Rossello

Schedule of events

Day 1:
  • Implementation Travel Team arrives in Don Juan and moves in with host families
  • Meet community members and contractors about the implementation process
  • Team familiarizes themselves with the work area and the school
Picture
Arriving at the School
Day 2:
  • Team 1 met with contractors at the work site and work on the piping schematic and video of site
  • Team 2 purchased construction materials in Santo Domingo​
​Day 3:
  • Finalized piping schematic
  • APMAE meeting with community about informing and familiarizing the community about the implementation process
  • Materials for piping is brought to work site
Day 4:
  • ​Team 1 visited the water treatment site
  • The trenches in which the pipes go were not dug deep enough, so team 1 had to dig the trenches deeper
  • Team 2 picked up the supplies and materials for the piping
  • Bonded with community
Day 5:
  • Prepared for implementation of pipes by cutting and fitting the pvc pipes
  • Pipes were not secured in place or together, but the layout was finished by the end of the day
Picture
Preparing to Cut Piping
Picture
Discussing Best Method for Diagonal Pipe Connections
Day 6:
  • Finalized pipe configurations and schematics
  • Glues pipes together to ensure pipe connections
  • The team also did the system shock calculations
Day 7:
  • ​The first pressure test was done on the pipes
  • The team also updated the fittings on the well pump to make the connections between the pipes and the well more secure
  • The gluing of the pipes was finished
Day 8:
  • More pressure tests were done
  • The trenches holding the pipes are filled in with sand
  • The team shocked the system conducted the first bacteria test on the system 
Picture
Covering of Trenches
Picture
Preparing Bacterial Tests
Day 9:
  • More bacteria tests and chlorine tests are done
  • Results from bacteria tests were worse than expected due to sanitation and plumbing issues in the school
  • Cleaned out tinacos in the community
Day 10:
  • Connection from pipe system to the school mural (top of page)
  • Mural is made as a community engagement activity
  • Worked on dosing the pump set up with chlorine
  • Community workshops and training focused on maintaining water pumping and chlorination systems
Picture
Community Members and Mural
Day 11:
  • The team conducted the final chlorination test
  • The results from the second bacteria test went much better than the first time around
  • Adjustments were made on the dosing of the pumping system
  • Everyone said their goodbyes as the team prepared to leave
Powered by Create your own unique website with customizable templates.
  • Home
  • About
    • Leadership 2023
    • Leadership 2022
    • Leadership 2021
    • Leadership 2020
    • Leadership 2019
    • Leadership 2018
    • Leadership 2017
  • Projects
    • Dominican Republic >
      • 1st Assessment Trip
      • 2nd Assessment Trip
      • Implementation Trip
      • First Monitoring Trip
      • Second Monitoring Trip
      • Third Monitoring Trip
    • Tanzania
    • Taproots (Local)
    • Grand Challenge Design
  • Newsletters
  • Gallery
  • Blog